The construction program

STEP 1 : Preliminary studies (1993-1996)

Ingeneering, preparation of the blueprint for contracting companies and development of the building site (September 1993 – April 1997)

  • Examination of the regulations
  • Preliminary technical studies : plans of the shape, estimation of the weight, stability, ...
  • Drawing of the plans and preparation of the call for contractors
  • Development of the building site : working and visiting areas, ...
 

STEP 2 : drawing of the shapes, building of the framework (1997-2000)

Official inauguration of the works with the fixing of the keel, July 4, 1997.

  • Drawing of the shapes, building of the templates
  • Building of the keel and the stern-post
  • Building of the rib all the way to the stem
  • Fixing of the keelson
  • Beggining of the cargo batten and the planks
 

STEP 3 : superstructure and deck construction (2000-2008)

  • Fixing of the planks and the cargo batten at first in skylight
  • Beam filling of the decks
  • Building of the decks
  • Inside planking
 

STEP 4 : Planking, caulking, and rigging (2009-2011)

    • Planking and caulking on the hull
    • Beginning of rigging (masts, yards, sails)
    • Finishes of the hull (back-bridge, sculptures, ...) 
 

STEP 5 : Final stage (2012-2013)

  • End of rigging
  • Launching of the hull
  •  Fitting of modern equipments
  • Artillery
  • Tests & certifications

 

STEP 6 : Target 2014

  • Trials at sea
  • Departure for the voyage spring 2014

 

 