The construction program

STEP 1 : Preliminary studies (1993-1996)

Ingeneering, preparation of the blueprint for contracting companies and development of the building site (September 1993 – April 1997)

  • Examination of the regulations
  • Preliminary technical studies : plans of the shape, estimation of the weight, stability, ...
  • Drawing of the plans and preparation of the call for contractors
  • Development of the building site : working and visiting areas, ...
 

STEP 2 : drawing of the shapes, building of the framework (1997-2000)

Official inauguration of the works with the fixing of the keel, July 4, 1997.

  • Drawing of the shapes, building of the templates
  • Building of the keel and the stern-post
  • Building of the rib all the way to the stem
  • Fixing of the keelson
  • Beggining of the cargo batten and the planks
 

STEP 3 : Fixing of the planks, the cargo batten, and the decks (2000-2007)

  • Fixing of the planks and the cargo batten at first in skylight
  • Beam filling of the decks
  • Building of the decks
  • Inside planking
 

STEP 4 : Finishing of the ship, rigging, artillery (2007-2011)

  • Finishing of the hull (back-bridge, sculptures, ...)
  • Rigging (masts, yards, sails, ...)
  • Adjustments and modern equipments
  • Artillery
  • Test & certifications
 